Enbridge satisfies Specified Measures of Inspection Officer Order (Amendment No. 2)
November 30, 2018
Enbridge (Westcoast) applied to lift pressure restrictions on the 36 inch pipeline segment 9L2 between Compressor Station 9 and the Huntingdon Meter Station, and the 30 inch pipeline segment 4L1 between Compressor Station 4A and Compressor Station 4B, on November 19, 2018, and November 23, 2018, respectively. A review of the Engineering Assessments submitted by the company in support of lifting these pressure restrictions has been completed. On November 30, 2018, the Inspection Officer notified the company that the Specified Measures of Inspection Officer Order NB-001-2018 (Amendment No. 2) specific to these pipeline segments have been satisfied.
- Notice of Measures Satisfied
- Inspection Officer Order NB-001-2018 (Amendment No. 2) was issued to Westcoast on November 16, 2018 to replace in its entirety, the previously issued amended Inspection Officer Order.