2023–24 Annual Report of the Commission of the Canada Energy Regulator – Appendix D: Time Limits
2023–24 Time Limits
The following graphic and table show applications which were subject to time limits for processing as per the CER Act. All time limits were met in 2023-24.
Percentage of Decisions – Grouped by Days Remaining on Time Limits
Graphic description
Percentage of Decisions – Grouped by Days Remaining on Time Limits
< 50 days Remaining |
50 – 100 days Remaining |
> 100 days Remaining |
---|---|---|
9% |
27% |
64% |
Under the CER Act, the Lead Commissioner must set a time limit for certain types of applications. The time limit must not exceed the maximum number of days stated in the CER Act. The Commission must complete its assessment and make its recommendation or decision within this time limit. The standard time limits set by the Lead Commissioner can be found on the CER website.
Applications processed subject to time limits:
Legislation |
Application Type |
Time Limit |
Application |
Days from Completeness to Decision Issued |
Decision |
---|---|---|---|---|---|
CER Act s 214 | Small Pipeline Infrastructure - Category C | 300 days from application complete | Westcoast Energy Inc. - Upper South Taylor Hill Horizontal Directional Drill Pipe Replacement | 106 | [Filing C23949] |
CER Act, |
Small Pipeline Infrastructure – Category B |
210 days |
Twin Rivers Paper Company Inc. – Application for the relocation of Pulp and White Water Pipelines under Section 214 |
85 |
|
CER Act s 214 |
Small Pipeline Infrastructure - Category B |
210 days from application complete |
NOVA Gas Transmission Ltd. – Application for the Willow Valley Interconnect |
44 |
|
CER Act s 214 |
Small Pipeline Infrastructure - Category C |
300 days from application complete |
Trans Mountain Pipeline ULC - Application for the Coquihalla Crossing No. 10 Replacement Project |
58 |
|
CER Act s 214 | Small Pipeline Infrastructure - Category B | 210 days from application complete | NOVA Gas Transmission Ltd. - Mildred Lake West Sales Meter Station Project | 70 | [Filing C25451] |
CER Act s 214 |
Small Pipeline Infrastructure - Category B | 210 days from application complete | Westcoast Energy Inc. - Trutch Creek HDD Pipe Replacement Project | 84 | [Filing C25609] |
CER Act s 183 |
Large Pipeline Infrastructure | 450 days from application complete | NorthRiver Midstream NEBC Connector GP Inc. – NEBC Connector Project | 413 | [Filing C26744] |
CER Act s 214 | Small Pipeline Infrastructure - Category A | 130 days from application complete | NOVA Gas Transmission Ltd. - Wilkin Lake Receipt Meter Station Project | 37 | [Filing C27689] |
CER Act s 214 | Small Pipeline Infrastructure - Category C | 300 days from application complete | NOVA Gas Transmission Ltd. – Application for the Grande Prairie Mainline Loop No. 4 (Valhalla North Section) and Berland River Compressor Station C3 Unit Addition | 115 | [Filing C27795] |
CER Act s 214 | Small Pipeline Infrastructure - Category A | 130 days from application complete | TransCanada PipeLines Limited – Regina South Meter Station Project | 42 | [Filing C28060] |
CER Act s 214 |
Small Pipeline Infrastructure - Category A | 130 days from application complete | NOVA Gas Transmission Ltd. - Iosegun Sales Meter Station Project | 35 | [Filing C28407] |